Replacement of Chiller Plant - Rooftop

Location:
SHEILA JOHNSON DESIGN CENTER
2 W 13TH - BUILDING L
66 FIFTH - BUILDING N
Roof

Scope of Work:
The project included the removal of the old unused absorption chiller  and creating the infrastructure for the chiller water at 66 Fifth ave, The new chiller was installed in the unused former water tank room located at the roof level and crating available space for Parson programs at the cellar at 2 West 13th.

Timeline:
Project completion: July 16, 2016.